Nova Square Business Complex – Construction Progress

Nova Square Business Complex – Construction Progress

Excavation and piling works

updated on 18/12/2025
Excavation and piling works began, forming the base for the project's foundations.
.

Concrete pouring begins on site

updated on 11/03/2026
Concrete pouring started on site on Gamal Abdel Nasser Axis.
.

Reinforced footings and garage basement columns

updated on 20/05/2026
The reinforced footings were completed on 11 May, followed by rebar and formwork for the Nova 1 garage basement columns, and casting of the concrete columns began on 20 May 2026.
.

Lower basement columns

updated on 13/09/2026
The project moved to a new stage with the casting of the lower basement columns.
.

Lower basement columns completed

updated on 20/09/2026
Casting of the remaining lower basement columns was completed.
.